Why is the main Option part of the question?
NEC's 23 September 2024 explanation describes Defined Cost as Option-specific and distinguishes the short schedule used in priced Options A and B from the cost schedules in reimbursable Options. It also distinguishes purposes such as interim payment and compensation event assessment. Read the actual contract and amendments rather than transferring a rule between them.
Pre-Bid Review is independent and is not affiliated with NEC. This article is not legal advice. A qualified contracts professional and legal adviser must assess project-specific entitlement, records and proposed departures.
Sources: NEC Contracts: Differences between defined and disallowed cost in NEC3 and NEC4, 23 September 2024
What should the tender team establish before pricing?
Map the records the proposed mechanism needs, who controls them and whether the bid team can provide them. A valid invoice can coexist with an unresolved contractual cost classification. Keep accounting payment status separate from the contractual assessment.
| Field | Evidence | Review |
|---|---|---|
| Contract basis | Form, edition, Option and amendments | Use the actual proposed documents |
| Purpose | Interim payment or change assessment | Do not transfer rules silently |
| Component | Applicable schedule reference | Check the precise cost description |
| Record | Invoice, allocation and supporting evidence | Show connection to the work |
| Treatment | Authorised inclusion, exclusion or open issue | Do not decide from an invoice alone |
| Bid action | Records plan or proposed clarification | Obtain contracts approval |
What does an evidence gap look like?
Illustrative example. A fictional electrical contractor has an equipment invoice coded to a general business account. Its proposed project assessment needs evidence of the relevant work allocation. The invoice proves a charge exists, but the review file does not explain which project activity it supports or the applicable cost component.
The reviewer requests the allocation evidence and an authorised contractual determination. This does not mean the cost is automatically disallowed or recoverable. No real cost, entitlement, deadline or clause wording is supplied by the example.
How does this improve the pre-bid decision?
Identify records ownership and unresolved interpretations before the commercial position is approved. Where the proposed record requirement cannot be met, raise a specific clarification or proposed departure through the tender procedure rather than assuming ordinary bookkeeping is sufficient.
Retain the approved decision and its source alongside the estimate basis. Do not reproduce licensed contract schedules or treat this matrix as an official NEC form.
Common questions
What else should the bid team know?
Does a paid invoice establish Defined Cost?
No. Its contractual treatment and supporting allocation still need review.
Can an Option A explanation be copied into every Option?
No. Confirm the actual Option and assessment purpose.
Does missing evidence automatically decide entitlement?
No. Obtain the authorised determination under the actual agreement.