What distinction does the publisher make?
The NEC publisher's When does the employer take over the works? FAQ distinguishes Completion, concerning the state of the works, from take over, concerning use. Its ECC Option A example uses Works Information terminology and discusses project-manager certification as well as contract-data qualifications.
Pre-bid Review is independent and is not affiliated with NEC. The example is not a universal rule for every edition or amended contract. This article is document-control guidance, not legal advice. A contracts professional and legal adviser must assess the actual executed terms.
Sources: NEC Contracts: NEC Contracts: When does the employer take over the works?, checked 22 October 2026
Which milestone records should be kept apart?
Do not compress readiness, certification, use and a later request into a single handed-over date.
| Record | Evidence to retain | Question for qualified review |
|---|---|---|
| Completion basis | Applicable definition and required work | What state is required? |
| Certification | Actual authorised record | What was certified and when? |
| Take over | Use and applicable certification evidence | Which part or works? |
| Contract data | Relevant qualifications and amendments | What changes the process? |
| Additional request | Exact instruction or request | Existing scope or proposed change? |
| Open work | Item and actual review status | What effect does it have? |
How can a single-date tracker hide a dispute?
Illustrative example. A fictional electrical package tracker marks handover complete because the contractor says the specified work is finished. A user group later requests an additional feature, and the tracker overwrites the same field with the date of that request.
The reviewer restores the chronology without deciding the dispute. It retains the original completion claim, the actual certification evidence, the use or take-over record and the separate request. The contracts reviewer then assesses their effect under the executed terms.
What should the pre-bid question ask?
Check whether the proposed terms and response schedules make these milestones and responsibilities clear. Record an ambiguity as a clarification or proposed departure for qualified approval, with the source document and actual wording referenced.
Do not infer a payment entitlement, release of security, deadline or right to defer defects from this article. Those consequences depend on the actual contract and facts.
Common questions
What else should the bid team know?
Is a contractor completion claim the certification itself?
No. Retain the actual required authorised record.
Does use alone resolve every Completion question?
No. The contract basis and separate evidence need review.
Does this worksheet decide a contractual dispute?
No. It is not legal advice or an entitlement determination.