Which distinction do the published FAQs make?

NEC's NEC4 ECC proposal FAQ explains that design responsibility is allocated through the Scope and that a change to that allocation needs the relevant instruction. Its separate Design Acceptance FAQ, framed around an ECC Option C example using Works Information terminology, says accepting the contractor's design does not change its liability for that design.

These public explanations need to be read in their actual context. Pre-bid Review is independent and is not affiliated with NEC Contracts. This article is not legal advice, does not reproduce contract clauses and does not decide liability under amended terms.

Sources: NEC Contracts: NEC Contracts FAQ: When is it a contractor's proposal?, checked 20 October 2026, NEC Contracts: NEC Contracts: Design Acceptance FAQ, ECC Option C example

What should the responsibility register separate?

Use the actual issued contract, edition, amendments and Scope. Record the source of the design allocation rather than infer it from a drawing stamp or an informal email.

What should the responsibility register separate?
ControlEvidenceQuestion
AllocationActual Scope requirementWho is assigned this part of design?
SubmissionRequired design deliverableWhat must be submitted and when?
AcceptanceActual authorized communicationWhat was accepted?
ChangeInstruction and revised ScopeDid the allocation itself change?
InterfacesNamed adjoining design dutiesIs any boundary unresolved?
ReviewContracts and legal dispositionWhat can the tender actually assume?

How can an accepted solution leave the allocation unresolved?

Illustrative example. A fictional contractor proposes a revised electrical equipment arrangement. A communication records acceptance of the proposal, but the bid register simply changes the design owner from client to contractor without identifying the actual Scope instruction or revised responsibility.

The reviewer restores the allocation as unresolved, links the proposal, acceptance and current Scope, and asks the authorized contracts owner to reconcile them. The example does not conclude that the client or contractor owns the design; that requires the actual contract and instruction history. It also gives no permission to start work or omit a required submission.

What closes the pre-bid issue?

Retain the approved allocation, any accepted departure and the matching price and programme assumptions. If the proposed solution changes technical interfaces but not contractual responsibility, record those as different decisions. Acceptance status and design assurance are not interchangeable fields.

Ask a contracts professional and legal adviser to resolve liability and amended terms. Technical acceptance and statutory duties need their own authorized review. Engineering sign-off is performed only by the registered engineer on the job.

Common questions

What else should the bid team know?

Does an accepted drawing automatically transfer design responsibility?

Do not infer a transfer from acceptance alone.

Does this worksheet determine liability?

No. Obtain the actual contract-specific legal review.

Are proposal acceptance and a Scope instruction the same record?

Keep their actual functions and references separate.