Which pricing option does this explanation concern?
NEC's 18 June 2024 introduction describes Option A payments by completed priced activities or groups. It contrasts this with the different Defined Cost approach discussed for other options. Merely seeing an activity schedule does not establish that every contract has the same payment calculation.
Pre-bid Review is independent and is not affiliated with NEC Contracts. This article is not legal advice. The contract and commercial owners must confirm the actual form, main option, schedules, grouping, amendments and assessment requirements.
Sources: NEC Contracts: NEC Contracts: NEC4 ECC pricing provisions, 18 June 2024
What should a pre-bid payment-basis register contain?
Keep the programme's progress forecast separate from the evidence needed under the actual payment mechanism. Do not change agreed activity definitions in a workbook and assume the contract has changed.
| Register field | Evidence to retain | Cash-flow question |
|---|---|---|
| Contract basis | Actual form, option and amendments | Which payment mechanism applies? |
| Activity identity | Priced activity and any grouping | What must be completed together? |
| Completion basis | Applicable requirements and evidence | What closes the activity? |
| Assessment | Actual assessment dates and status | Which period can recognise it? |
| Forecast | Progress and expected completion | Is an unfinished activity being prorated? |
| Exceptions | Authorised commercial or legal disposition | What is still an assumption? |
How can a progress percentage overstate the assumed activity contribution?
Illustrative example. A fictional unamended Option A review has a 100 cost-unit activity that remains incomplete at assessment. The programme reports 60 percent physical progress. Entering 60 cost units as its automatic activity contribution applies a proportional rule that the described completed-activity mechanism does not establish.
The reviewer records the activity as incomplete for that specific mechanism and asks the contract owner to confirm its treatment. This is not a calculation of the total amount due: other activities, contractual adjustments and the actual payment provisions remain separate. It does not permit withholding a sum that the real contract requires.
How should the tender team improve the forecast?
Before tender, review whether the proposed schedule and cash-flow model reflect the actual mechanism and delivery plan. Refer unsuitable grouping or unclear completion evidence through the permitted clarification process. Only authorised agreement can change the contract basis.
Keep the original assumptions and approved clarification with the estimate. A programme percentage, invoice or accepted programme is not a substitute for the particular payment evidence required.
Common questions
What else should the bid team know?
Is 60 percent progress automatically 60 percent of an activity price?
Not under the completed-activity approach described here.
Does every NEC main option pay in the same way?
No. Check the actual option and amendments.
Does this worksheet calculate the whole amount due?
No. It isolates one activity-basis assumption.