What distinction does the publisher explain?

NEC's FAQ concerns an NEC4 ECC Option C change in scope where the overall forecast has not moved. It explains that the whole-works forecast does not determine the event assessment; savings elsewhere can leave the total unchanged even when that event has an additional cost effect.

Pre-bid Review is independent and is not affiliated with NEC Contracts. This is not legal advice. Confirm the actual form, option, edition, amendments, event and communications with a qualified contracts professional and legal adviser. Do not transfer the FAQ to every contract.

Sources: NEC Contracts: NEC Contracts: Forecasting defined cost FAQ, NEC4 ECC Option C example, checked 21 October 2026

Which records should a bidder keep distinct?

The tender review should establish the information needed by the applicable mechanism, rather than promise that a total-cost dashboard can replace contract administration.

Which records should a bidder keep distinct?
RecordScopeReview question
Whole-works forecastExpected overall outcomeWhich snapshot and assumptions?
Event identitySpecific instruction or circumstanceWhat changed and when?
Event assessmentEffect under the applicable mechanismWhich actual or forecast basis?
Other movementsSeparate savings or changesWhy did the total move or stay flat?
CommunicationsRelevant formal recordsWhat was actually notified or agreed?
DispositionQualified assessment referenceWhich record was implemented?

How can offsetting movements hide an event?

Illustrative example. A fictional overall forecast is 1,000 cost units. One identified change adds 40 units to the forecast while a separate saving reduces it by 40 units. The new total is still 1,000. That arithmetic does not establish that the change itself had zero effect.

The reviewer retains both movements and the event-specific evidence. These fictional units are not a compensation event valuation, a cost entitlement or a prediction of pain or gain share. The actual contract determines how each effect and relevant date is assessed.

What belongs in a pre-bid clarification?

Where the tender asks for cost reporting, identify which forecast, event records and supporting evidence are expected, who supplies them and how revisions are controlled. Raise ambiguous references to a single budget as an issue for qualified review.

Do not treat a reporting template as an amendment to the contract. Keep pricing assumptions and proposed departures linked to the actual tender wording and authorised decisions. This article is not legal advice.

Common questions

What else should the bid team know?

Does a flat total prove zero event cost?

No. Separate movements can offset one another.

Can an overall forecast replace event assessment?

No. Confirm the applicable contract mechanism and event evidence.

Is the example a valuation or legal conclusion?

No. It demonstrates an arithmetic distinction for qualified review.

Primary sources

  1. NEC Contracts: Forecasting defined cost FAQ, NEC4 ECC Option C example, checked 21 October 2026NEC Contracts