What does the publisher example establish?

NEC's Using the correct programme FAQ addresses an NEC4 ECC Option C example. On its stated assumption that a revised programme was issued after the event's dividing date, the publisher identifies the accepted programme current at that dividing date as the relevant assessment basis rather than the later issue.

Pre-bid Review is independent and is not affiliated with NEC Contracts. This article is not legal advice. The actual form, edition, amendments, event and communications need qualified contract review. The FAQ's assumption is not proof of the dividing date in another case.

Sources: NEC Contracts: NEC Contracts: primary reference checked 25 October 2026

How can the file-selection error occur?

Illustrative example. A fictional electrical package record identifies programme A as accepted on 2 March, an independently reviewed event dividing date of 10 March, and programme B issued on 14 March. The assessment workbook links B merely because its filename is newest.

The reviewer flags the mismatch and retains A, its acceptance evidence and the date determination for the responsible contracts reviewer. This example assumes the stated dates and status; it does not determine a real dividing date, programme acceptance, delay entitlement or amount due. A later programme can remain relevant to ongoing management without becoming the assessment baseline for this event.

Which fields should the version register retain?

A document issue date and its contractual status are separate facts.

Which fields should the version register retain?
RecordEvidence or interpretation
EventSpecific compensation-event identity
Date basisQualified determination and supporting communications
Programme identityExact file, revision and native reference
AcceptanceActual acceptance evidence and effective status
Assessment linkProgramme current at the identified dividing date
Later issuesSeparate issue and acceptance history
ReviewContract-specific decision and open questions

How should the pre-bid team use this distinction?

Check whether the proposed administration process can retain accepted programme versions and event-specific references. A shared folder that replaces old files with the latest revision may not preserve the evidence needed for later review. Agree responsibilities and controlled records before delivery.

This register does not calculate float, a critical-path delay or a compensation amount. Preserve the underlying programme and have qualified planning and contract owners carry out the actual assessment under the governing terms.

Common questions

What else should the bid team know?

Is the latest filename sufficient evidence?

No. Identify the relevant date and accepted status.

Does a later programme have no management purpose?

No. Keep its ongoing purpose separate from this event assessment basis.

Does this example establish a notice deadline?

No. The actual contract and communications need qualified review.

Primary sources

  1. NEC Contracts: primary reference checked 25 October 2026NEC Contracts