What does the publisher distinguish?

NEC's 5 December 2024 explanation discusses time risk allowances associated with particular operations and the terminal float between planned Completion and the required Completion Date. It recommends a reasoned and visible allowance methodology. Confirm the actual contract form, edition and amendments rather than treating every programme buffer as interchangeable.

Pre-Bid Review is independent and is not affiliated with NEC. This article is not legal advice. A qualified planner, contracts professional and legal adviser must assess the project-specific programme, rights and proposed tender position.

Sources: NEC Contracts: NEC Contracts: Why you need reasonable time risk allowances in NEC contracts, 5 December 2024

Which references should the bid register separate?

Keep the programme's actual calendar and logic with the allowance record. A risk allowance already included in an activity duration must not be counted again as an additional end-of-programme duration. A bar called contingency needs an explanation of what it covers.

Which references should the bid register separate?
Programme conceptRecord to retainReview distinction
Activity durationOperation and calendarDoes it already include time risk?
Time risk allowanceOperation, reason and stated amountWhat uncertainty does it address?
Planned CompletionProgramme revision and logicWhat does the current plan forecast?
Completion DateActual contractual referenceHas it been formally changed?
Terminal floatGap on the consistent calendarKeep separate from activity allowance
Approval statusSubmission and authorised outcomeDo not infer entitlement from a label

How can a simplified plan double-count the allowance?

Illustrative example. A fictional linear operation has six working days of planned task time plus two working days of identified time risk, giving an eight-working-day activity duration. In the same invented programme and working-day calendar, planned Completion falls on day 45 and the required Completion Date is day 50. The simplified terminal gap is five working days.

The two days are already inside the activity's eight days; adding them again at the end would change the represented plan. The five-day terminal gap is a separate comparison. These numbers illustrate record distinctions, not a real critical-path analysis or a method for awarding delay entitlement.

What belongs in a pre-bid clarification?

Ask for the applicable programme requirements and the expected visibility of time risk allowances where the tender documents are unclear. Have the planner explain allowance placement and assumptions. Keep unanswered issues visible before approving the bid programme or narrative.

Do not turn the example into a universal percentage, ownership ruling, acceptance decision or compensation-event assessment. Retain the authorised contractual and programme decisions together without reproducing licensed contract text.

Common questions

What else should the bid team know?

Is terminal float the same as an activity's time risk allowance?

No. Record their different locations and purposes.

Should an allowance inside a duration be added again at the end?

Not as an unrecorded duplicate. Confirm the actual planning basis.

Does this example determine extension-of-time rights?

No. That requires project-specific planning and contractual assessment.

Primary sources

  1. NEC Contracts: Why you need reasonable time risk allowances in NEC contracts, 5 December 2024NEC Contracts