Which contract process does the source describe?
NEC's FAQ describes the NEC3 ECC acceleration mechanism as consensual. It distinguishes a request to provide a quotation from acceptance of that quotation, which changes the relevant prices and dates and accepts the revised programme.
Pre-bid Review is independent and is not affiliated with NEC. This is not legal advice. It does not extend the FAQ unchanged to NEC4, every main option, a subcontract or a contract modified by additional conditions. Have the actual executed contract and amendments reviewed by the designated contracts professional and legal adviser.
Sources: NEC Contracts: NEC Contracts: Detailing acceleration costs, NEC3 ECC FAQ, checked 21 October 2026
Which records should an acceleration review connect?
Start with the actual authorised communication and its purpose. A request to investigate an earlier date, a quotation request and an acceptance are different evidence states.
| State | Evidence | Review question |
|---|---|---|
| Request | Authorised communication | What is being requested? |
| Quotation | Actual proposal and assessment basis | What changes are offered? |
| Programme | Proposed revised sequence and dates | What does the price assume? |
| Review | Contract-specific commercial and technical assessment | What remains unresolved? |
| Acceptance | Authorised decision under the actual contract | Which changes were accepted? |
| Reconciliation | Updated controlled records | Do programme and commercial records agree? |
How can a planning date become an unsupported commitment?
Illustrative example. A fictional EPC team receives a request to quote an earlier finish. Its bid tracker immediately replaces the contractual Completion Date with the requested date, although no quotation or acceptance has been recorded. A planning aspiration has become a false statement of contract status.
The reviewer retains the current contractual date, records the proposed earlier date separately and links the request to the quotation owner. This does not decide an entitlement, require acceleration or justify ignoring a valid instruction under a different contractual process.
What should be checked before the tracker is closed?
Reconcile the specific accepted proposal, its cost assessment and revised programme against the actual approval. Keep unresolved assumptions about working patterns, resources and interfaces visible. Do not treat an ordinary programme acceptance or an email discussing a price as proof that this acceleration process was completed.
The register supports evidence assembly and human review. Qualified advisers decide the legal effect of the actual communications and contract terms.
Common questions
What else should the bid team know?
Does the request alone prove an accepted earlier Completion Date?
No. Retain the separate quotation and acceptance evidence.
Does this article decide an acceleration entitlement?
No. Obtain contract-specific professional advice.
Can an NEC3 FAQ be applied unchanged to another contract?
No. Verify the actual form, edition and amendments.